Adds $12,508 to North American Fence & Railing's contract for fence work at Coliseum Prep's interim housing
The board approves a change order for fence and gate work at the Coliseum College Preparatory Academy Interim Housing Project, raising the contract limit from $23,000 to $35,508. The work includes moving a chain-link fence and adding a panic bar to a pedestrian gate. The end date also moves from August 30, 2025 to November 30, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Notes on the official text
- The text describes the extension from August 30, 2025 to November 30, 2025 as 93 additional calendar days, but that span is 92 days (93 if counted inclusively); the stated end date of November 30, 2025 governs.
- Vendor / partner
- North American Fence & Railing, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 27, 2025 – Nov 30, 2025
- This vote
- $12,508
- Previous total
- $23,000
- New total
- $35,508
- Schools
- Coliseum College Preparatory Academy
- Funding
- Building Fund 21 Measure Y
- Resource / site
9655/232- Vendor no.
003105- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-2430· agendaP.-2- Outcome
- Adopted on the General Consent Report, Nov 12, 2025
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and North American Fence & Railing, Inc., Oakland, CA, for the latter to: PCO 1: Reinstalled a 10’ high chain-link fence with a 1” mesh (22 linear feet) along with a pedestrian gate. Modify the existing pedestrian gate by adding a panic bar and reconfiguring the latch and ram cylinder; and PCO 2: Remove the existing 10’ high galvanized chain-link fence with 1” mesh (33 LF) and a 48” wide pedestrian gate. Relocate and install a 7” high chain-link fence with 2” mesh at a new location, reusing the posts, rails, and gate from the original fence, in the not to exceed amount of $12,508.00, increasing the Agreement not to exceed amount from $23,000.00 to $35,508.00, and extending the term of the Agreement from March 27, 2025 through August 30, 2025 to November 30, 2025 (an additional 93 calendar days), for the Coliseum College Preparatory Academy Interim Housing Project. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report