Hires Terraphase for $96,935 in stormwater pollution-control planning for the Coliseum College Prep expansion
Terraphase Engineering will provide Stormwater Pollution Prevention Plan consulting for the Coliseum College Preparatory Academy site expansion. The $96,935.00 includes an $8,812.00 contingency fee. The district rejected all other proposals and selected Terraphase; work runs December 11, 2025 through June 30, 2028.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Terraphase Engineering, Inc. · Oakland, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Dec 11, 2025 – Jun 30, 2028
- This vote
- $96,935
- Schools
- Coliseum College Preparatory Academy
- Funding
- Building Fund 21 Measure Y
- Resource / site
9655/232- Vendor no.
004240- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-2568· agendaP.-1- Outcome
- Adopted on the General Consent Report, Dec 10, 2025
Official text
Approval by the Board of Education of a General Services Agreement by and between the District and Terraphase Engineering, Inc., Oakland, CA, rejecting all other RFQ/Ps, for the latter to provide Stormwater Pollution Prevention Plan (SWPPP) consulting services, as further described in Exhibit A of the Agreement, incorporated herein by reference as though fully set forth, for the Coliseum College Preparatory Academy Site Expansion Project, in the amount of $96,935.00, which includes a contingency fee of $8,812.00, as the selected consultant, with work scheduled to commence on December 11, 2025, and scheduled to last until June 30, 2028.
History