Extends Asbestos Management Group's demolition contract to June 30, 2026 at no added cost
Approves a change order that extends the contract term from December 31, 2025 to June 30, 2026, an added 181 days, for the Ralph Bunche and Hillside site demolition projects. The work was paused so another contractor could finish urgent hazardous waste cleanup after a fire. No added money is stated.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Asbestos Management Group · San Leandro, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jul 14, 2025 – Jun 30, 2026
- Schools
- Ralph Bunche, Hillside
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9658 223- Vendor no.
000500- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-3049· agendaP.-2- Outcome
- Adopted on the General Consent Report, Jan 28, 2026
Official text
Approval by the Board of Education of Change Order (CO) No. 2, Agreement Between Owner and Contractor by and between the District and Asbestos Management Group, San Leandro, CA, providing the latter an extension of the term of the Agreement, from July 14, 2025, through December 31, 2025, to June 30, 2026 (an additional 181 calendar days), due to a pause for other priority site remediation by other contractor (hazardous waste cleanup due to fire) to allow for completion of the Project, as identified in the CO No. 1, for the Ralph Bunche and Hillside School Sites Demolition Projects. All other terms and conditions of the Agreement remain in full force and effect.