Adds $16,171.80 for Applied Materials & Engineering's testing at Coliseum College Prep expansion
This amendment to a master agreement with Applied Materials & Engineering Inc. covers material testing and special inspection services for the Coliseum College Preparatory Academy Site Expansion Project. The not-to-exceed amount is $161,718, which includes $16,171.80 for additional services. The work starts March 12, 2026 and ends when the assigned project is complete.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Applied Materials & Engineering Inc. · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 12, 2026
- This vote
- $16,171.80
- New total
- $161,718
- Schools
- Coliseum College Preparatory Academy
- Funding
- Building 21 Measure Y
- Resource / site
9657/232- Vendor no.
00468- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-0314· agendaP.-2- Outcome
- Adopted on the General Consent Report, Mar 11, 2026
Official text
Approval by the Board of Education of Amendment No. 1, Master Agreement For Material Testing and Special Inspection Services by and between the District and Applied Materials & Engineering Inc., Oakland, CA, for the latter to provide material testing and special inspection services for the Coliseum College Preparatory Academy Site Expansion Project, in the not-to-exceed amount of $161,718.00, which includes a not-to-exceed amount of $16,171.80 for additional services, commencing on March 12, 2026, and shall end upon the completion of assigned project pursuant to the Agreement. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report