Cuts $8,000 from Asbestos Management Group's demolition contract at Ralph Bunche and Hillside sites
A deductive change order removes underground utility location, excavation, capping and backfilling at four locations from Asbestos Management Group's scope. It lowers the contract's not-to-exceed amount from $612,000 to $604,000 for the Ralph Bunche and Hillside school site demolition projects.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Asbestos Management Group · San Leandro, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $8,000
- Previous total
- $612,000
- New total
- $604,000
- Schools
- Ralph Bunche, Hillside
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9658 223- Vendor no.
000500- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-0441· agendaP.-1- Outcome
- Adopted on the General Consent Report, Mar 25, 2026
Official text
Approval by the Board of Education of Change Order No. 3, Agreement Between Owner and Contractor by and between the District and Asbestos Management Group, San Leandro, CA, authorizing a deductive Change Order deleting from the Scope of Work underground utility location services and markings, excavation, capping and backfilling at four (4) locations, in the amount of -$8,000.00, reducing the Agreement not to exceed amount from $612,000.00 to $604,000.00, as specified in the COR No. 3, for the Ralph Bunche and Hillside School Sites Demolition Projects. All other terms and conditions of the Agreement remain in full force and effect.