Gives N G Builder Company 64 more days, at no added cost, on the Highland play yard project
This change order extends the contractor's deadline for the Highland Child Development Center play yard improvements from February 25, 2026 to April 30, 2026, an additional 64 calendar days. The delay is due to late delivery of play equipment, as identified in a preliminary change order. There is no additional cost.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- N G Builder Company · Santa Clara, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Dec 11, 2025 – Apr 30, 2026
- Schools
- Highland Child Development Center
- Funding
- OCI Oakland Children Initiative
- Resource / site
9186 815- Vendor no.
009085- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-0682· agendaO.-8- Outcome
- Adopted on the General Consent Report, Apr 22, 2026
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Nicholas Guiterrez dba N G Builder Company, Santa Clara, CA, extending the term of the Agreement from December 11, 2025, through February 25, 2026, to April 30, 2026 (an additional 64 calendar days), due to delay in play equipment procurement, as identified in the PCO No. 1, at no additional cost, for the Highland Child Development Center Play Yard Site Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report