Adds $96,948.50 and more time for Atlas Technical Consultants' soil work at Fremont High
The district is adding $96,948.50 to its agreement with Atlas Technical Consultants, raising the contract limit from $6,842.50 to $103,791. The added money covers more soil engineering and extra work caused by unforeseen soil pumping and added compaction requirements at the Fremont High School Modernization Project. The agreement also runs 184 days longer, now ending December 31, 2026.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Atlas Technical Consultants, LLC · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Oct 23, 2025 – Dec 31, 2026
- This vote
- $96,948.50
- Previous total
- $6,842.50
- New total
- $103,791
- Schools
- Fremont High School
- Funding
- Fund 21 Building Fund Measure J
- Resource / site
9650 302- Vendor no.
007113- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-0695· agendaP.-4- Outcome
- Adopted on the General Consent Report, Apr 22, 2026
Official text
Approval by the Board of Education of Amendment No. 1, Agreement for Engineering Services by and between the District and Atlas Technical Consultants, LLC, Oakland, CA, for the latter to provide additional geotechnical engineering services and added services required for unforeseen condition of soil pumping and additional compaction requirements, as outlined in the Proposal dated January 21, 2026, attached to this Amendment as Exhibit A, for the Fremont High School Modernization Project, in an additional amount of $96,948.50, increasing the Agreement not-to-exceed amount from $6,842.50 to $103,791.00, and extending the term of the Agreement from October 23, 2025 through June 30, 2026 to December 31, 2026, an additional 184 calendar days. All other terms and conditions of the Agreement remain in full force and effect.