Adds $403,609.01 to settle changed-work costs on Manzanita Elementary's Cal Fire project
This change order pays Native Soil, Inc. a negotiated settlement for work that was unforeseen, requested by the District, or driven by design changes, listed in preliminary change orders (PCOs) 1 through 25. It settles disputed costs and fully resolves the contractor's claims. The contract price rises from $567,500 to $971,109.01.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Native Soil, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $403,609.01
- Previous total
- $567,500
- New total
- $971,109.01
- Schools
- Manzanita Elementary School
- Funding
- Fund 1 General Fund CAL Fire
- Resource / site
7822 179- Vendor no.
007827- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-0881· agendaO.-15- Outcome
- Adopted on the General Consent Report, May 13, 2026
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Native Soil, Inc., Oakland, CA, awarding compensation to the latter for various scopes of changed work order work which were unforeseen, owner requested, or driven by scope and design modifications, as described in documentation, identified in (PCOs) Nos. 1 through 25, as a mutually negotiated and agreed upon settlement of disputed costs between Owner and Contractor which are a full and final resolution of any and all claims made or could have been made, with respect to the Manzanita Elementary School Cal Fire Implementation Project, in the not-to-exceed settlement amount of $403,609.01, increasing Agreement price from $567,500.00 to $971,109.01, via the Division of Facilities Planning and Management. All other terms and conditions of the Agreement remain in full force and effect.