Ratifies up to $5,000 for Bay City Boiler to fix the Central Kitchen exhaust system
Bay City Boiler & Engineering replaced the kitchen exhaust blower and the nonfunctioning control system at the District's Central Kitchen, and serviced the make-up air unit to improve ventilation. The agreement covered October 1 to December 31, 2025 and was ratified after the work period.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Bay City Boiler & Engineering Co, Inc. · Hayward, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- Food, transportation & operations
- Term
- Oct 1, 2025 – Dec 31, 2025
- This vote
- $5,000
- Funding
- 5310 - Child Nutrition School Program
- Resource / site
5310-991- Vendor no.
000641- Presented by
- Chief Systems and Services Officer
- File
26-0919· agendaO.-19- Outcome
- Adopted on the General Consent Report, May 13, 2026
Official text
Ratification by the Board of Education of a Services Agreement 2025-2026 by and between the District and Bay City Boiler & Engineering Co, Inc., Hayward, CA, for the latter to replace the existing kitchen exhaust blower and the nonfunctioning control system to restore proper operation of the kitchen exhaust and make-up air systems at the District's Central Kitchen; inspect and service the make-up air package unit to ensure balanced airflow and improved ventilation within the kitchen space, via the Nutrition Services Department, for the period of October 1, 2025 through December 31, 2025, in an amount not to exceed $5,000.00.
History
- Adopted on the General Consent Report