After work beganRaises existing contractLarge increase
+$38Knew total $102K

Adds $38,201.02 and two months for King Construction Inspection on school solar projects

This amendment adds inspector-of-record work for the Solar Photovoltaics Phase 2 & 3 projects at five school sites. The inspector is the certified Division of the State Architect (DSA) inspector who checks materials and construction quality. The contract limit rises from $63,735.54 to $101,936.56, and the end date moves from April 30, 2026 to June 30, 2026.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Amendment
Category
School buildings & construction
Term
May 29, 2025 – Jun 30, 2026
This vote
$38,201.02
Previous total
$63,735.54
New total
$101,936.56
Schools
Horace Mann Elementary School, Oakland Academy of Knowledge, Madison Park Academy, Stonehurst Elementary School, Laurel Child Development Center
Funding
Building Fund 21 Measure Y
Resource / site
9657/136,69,820,215,177
Vendor no.
007828
Presented by
Deputy Chief, Facilities Planning and Management
File
26-0662 · agenda P.-2
Outcome
Adopted on the General Consent Report, May 27, 2026

Official text

Approval by the Board of Education of Amendment No. 2, Agreement for Inspector of Record Services for Construction by and between the District and King Construction Inspection, Inc., Oakland, CA, for the latter to provide additional Inspector of Record Services for Construction as the certified DSA Inspector of Record to oversee the quality of the materials and construction compliance with DSA requirements, for the Solar Photovoltaics Phase 2 & 3 at Horace Mann Elementary School, Oakland Academy of Knowledge, Madison Park Academy, Stonehurst Elementary School, and Laurel Child Development Center, as outlined in the Proposal dated April 23, 2026, attached to this Amendment as Exhibit A, in an additional amount of $38,201.02, increasing the Agreement not-to-exceed amount from $63,735.54 to $101,936.56, extending the term of the Agreement from May 29, 2025 through April 30, 2026 to June 30, 2026 (an additional 61 days), via the Division of Facilities Planning and Management. All other terms and conditions of the Agreement remain in full force and effect.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.