Extends N G Builder Company's Tubman play yard project through June 30, 2026 at no added cost
This change order gives N G Builder Company 59 more calendar days to finish the play yard improvements at the Harriet Tubman Child Development Center, moving the end date to June 30, 2026. The text cites rain and phasing the work so students can keep using the yard under early childhood education guidelines. No added money is stated.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- N G Builder Company · Santa Clara, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Feb 16, 2026 – Jun 30, 2026
- Schools
- Harriet Tubman Child Development Center
- Funding
- OCI Oakland Children Initiative
- Resource / site
9186 825- Vendor no.
009085- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1200· agendaD.-4- Outcome
- Adopted on the General Consent Report, Jun 24, 2026
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Nicholas Guiterrez doing Business as N G Builder Company, Santa Clara, CA, due to rainy and/or phase out to allow students access to the yard pursuant to Early Childhood Education (ECE) guidelines, extension of the term from February 16, 2026, through May 2, 2026 to June 30, 2026 (an additional 59 calendar days), as identified in PCO No. 1, for the Harriet Tubman Child Development Center Play Yard Site Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.
History
- Postponed to a Date Certain
- Failed
- Adopted on the General Consent Report
Also on the agenda: Jun 10, 2026, Jun 24, 2026
- Official record on Legistar
- 26-1200 Change Order No. 1, Agreement Between Owner and Contractor – Nicholas Guiterrez doing Business as N G Builder Company – Harriet Tubman Child Development Center Play Yard Site Improvement Project – Division of Facilities Planning and Management (6/
- 26-1200 Change Order No. 1, Agreement Between Owner and Contractor – Nicholas Guiterrez dba N G Builder Company – Harriet Tubman Child Development Center Play Yard Site Improvement Project – Division of Facilities Planning and Management (6/24/2024)