Adds $109,916 to N G Builder Company's contract for Emerson Elementary site improvements
This change order adds $109,916.02 for safety surfacing near the TK-K play structure, asphalt demolition, decomposed granite, garden fence removal and other extra work at Emerson Elementary School. The changes come from preliminary change orders (PCOs) 2 through 4. The contract price rises from $397,666.00 to $507,582.02.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- N G Builder Company · Santa Clara, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $109,916.02
- Previous total
- $397,666
- New total
- $507,582.02
- Schools
- Emerson Elementary School
- Funding
- Fund 01 General Fund ELOP
- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1470· agendaR.-44- Outcome
- Adopted on the General Consent Report, Jun 24, 2026
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Nicholas Guiterrez doing business as N G Builder Company, Santa Clara, CA, for the latter to Furnish and install PIP safety surfacing (TK-K play structure area); Asphalt demolition, DG installation, and garden fencing removal and Miscellaneous additional work, as identified in the PCOs No. 2-4, for the Emerson Elementary School Site Improvements Project, in the not to exceed amount of $109,916.02, increasing the Agreement price from $397,666.00 to $507,582.02. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report