Voted on separatelyMulti-year
$12.3Mnot to exceed

Pays Brailsford & Dunlavey up to $12.3M to run the Measure Y bond program through mid-2028

This agreement with Brailsford and Dunlavey, Inc. of Washington, DC covers bond program management, planning, coordination and construction management as the district finishes its Measure J bond program and starts its Measure Y bond program. The amount is not to exceed $12,301,629, with work scheduled from July 1, 2026 to June 30, 2028. It is paid from the Measure Y building fund.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Pulled from the consent vote. Adopted in its own vote on June 29 (5–1), instead of with the rest of the consent report.

· Not Discussed and/or Taken Up. Not Discussed and/or Taken Up.

· Adopted (passed). A motion was made by Vice President Bachelor, seconded by Director Latta that all Unfinished Business Items on this Agenda (R.-9, R.-10, R.-27, R.-28, R.-1, R.-2, R.-84, R.-94, R.-113, R.-115, R.-122, R.-226, R.-239, R.-248, R.-249, R.-62, R.-250), be considered concurrently, recorded separately and Adopted. The motion carried by the following vote:.

  • Maximus Simmons Absent
  • Marianna Smith Absent
  • Rachel Latta Aye
  • VanCedric Williams Aye
  • Mike Hutchinson Nay
  • Patrice Berry Aye
  • Clifford Thompson Absent
  • Valarie Bachelor Aye
  • Jennifer Brouhard Aye
Action
New agreement
Category
School buildings & construction
Term
Jul 1, 2026 – Jun 30, 2028
This vote
$12,301,629
Funding
Building Fund 21 Measure Y
Resource / site
9657/918
Presented by
Facilities Committee
File
26-1547 · agenda R.-250
Outcome
Adopted, Jun 29, 2026

Official text

Approval by the Board of Education of an Oakland Unified School District Measure Y Program Management Services Agreement by and between the District and Brailsford and Dunlavey, Inc., Washington, DC, for the latter to provide bond program management, planning, coordination, and construction management services through the completion of the District's Measure J Bond Program and the commencement and implementation of the Measure Y Bond Program, in the not to exceed the amount of $12,301,629.00, with work scheduled to commence on July 1, 2026, and scheduled to last until June 30, 2028, pursuant to the Agreement.

History

  1. Recommended Favorably (Facilities Committee)
  2. Not Discussed and/or Taken Up
  3. Adopted

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.

Get Updates

Your info is safe with us.