Raises existing contractLarge increaseText discrepancyMulti-year
+$36Knew total $94K

Adds $36,245.55 for extra concrete and shotcrete inspection at Fremont High's rebuild

Inspection Services, Inc. will do more testing and inspection work on the Fremont High School Modernization Project, including review of concrete mixes, sprayed-concrete (shotcrete) inspection and laminated-beam shop inspections. This raises the contract limit from $57,269.30 to $93,514.85. The service period runs from April 10, 2025 to December 31, 2026.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Discrepancy from the official text. The text calls the time period 'unchanged' but also lists 'April 10, 2025, through December 31, 2025, to December 31, 2026', leaving unclear whether the end date is extended to December 31, 2026. (Confirmed by a second, independent AI reading.)
Action
Amendment
Category
School buildings & construction
Term
Apr 10, 2025 – Dec 31, 2026
This vote
$36,245.55
Previous total
$57,269.30
New total
$93,514.85
Schools
Fremont High School
Funding
Fund 21 Building Fund Measure J
Resource / site
9650 302
Vendor no.
002199
Presented by
Deputy Chief, Facilities Planning and Management
File
26-1294 · agenda R.-1
Outcome
Adopted on the General Consent Report, Aug 12, 2026

Official text

Approval by the Board of Education of Amendment No. 2, Agreement for Materials Testing and Special Inspection Services by and between the District and Inspection Services, Inc., Berkeley, CA, for the latter to provide additional inspection services which include additional review of concrete mix designs, DSA shotcrete inspection, shotcrete preconcreting evaluation, shotcrete compression cores, and glulam shop inspections, as outlined in the Proposal dated April 29, 2026, attached to this Amendment as Exhibit A, in the additional not-to-exceed amount of $36,245.55, increasing the Agreement not-to-exceed amount from $57,269.30 to $93,514.85, for the unchanged time period of April 10, 2025, through December 31, 2025, to December 31, 2026, for the Fremont High School Modernization Project. All other terms and conditions of the Agreement remain in full force and effect.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.