Cuts $15,020.80 from Benyon's Oakland High turf contract after a field-base change
This change order lowers the price of Benyon Sports Surfaces' turf work at Oakland High School from $413,524.78 to $398,503.98. The district dropped a planned new base layer under the softball/baseball field in favor of a Brock Pad system, and the text also cites unforeseen repairs to the existing base layer. The district is buying through the California Multiple Award Schedules (CMAS), a state contract list, instead of running its own bid.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Benyon Sports Surfaces, Inc. · Fresno, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $15,020.80
- Previous total
- $413,524.78
- New total
- $398,503.98
- Schools
- Oakland High School
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9657/9000-304- Vendor no.
009594- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1598· agendaR.-9- Outcome
- Adopted on the General Consent Report, Aug 12, 2026
Official text
Approval by the Board of Education of Change Order No. 1, CMAS Purchase and Installation Agreement by and between the District and Benyon Sports Surfaces, Inc., Fresno, CA., for unforeseen repairs to the existing e-layer identified during construction activities and owner requested deduction of originally planned installation of a new e-layer at the softball/baseball field and replacement of it with a Brock Pad System, resulting in a deductive amount of $15,020.80, decreasing the Agreement price from $413,524.78 to $398,503.98. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report