Adds $28,985 for factory inspection of Skyline High field light poles
King Construction Inspection, Inc. will provide inspections during manufacturing of the light poles and concrete bases for the Skyline High School field lighting project, following Division of the State Architect (state school-construction review agency) guidelines. The contract limit rises from $23,387.50 to $52,372.50. Work runs August 13, 2026 to March 31, 2027.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- King Construction Inspection, Inc. · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Aug 13, 2026 – Mar 31, 2027
- This vote
- $28,985
- Previous total
- $23,387.50
- New total
- $52,372.50
- Schools
- Skyline High School
- Funding
- Building Fund 21 Measure Y
- Resource / site
9658/306- Vendor no.
007825- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1607· agendaR.-11- Outcome
- Adopted on the General Consent Report, Aug 12, 2026
Official text
Approval by the Board of Education of Amendment No. 2, Master Project Agreement for Inspector of Record Services by and between the District and King Construction Inspection, Inc., Oakland CA, for the latter to provide inspection services, pursuant to fee proposal dated July 10, 2026, which includes DSA-certified in-plant inspections during manufacturing of the light poles and concrete bases in accordance with DSA guidelines, for the Skyline High School Field Lighting Replacement Project, in an additional amount of $28,985.00, increasing the Agreement not-to-exceed amount from $23,387.50 to $52,372.50, with work scheduled to commence on August 13, 2026, and scheduled to end on March 31, 2027. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report