Adds $11,796 for concrete, toilet, conduit and lighting work at Markham Elementary restroom
This change order with Next Generation of Builders, LLC covers added work on the Markham Elementary School Boys Toilet Renovation Project: replacing a concrete slab found in poor condition, repairing a damaged toilet flange, adding ceiling conduit supports and upgrading light fixtures. The net addition is $11,796.39 after applying $1,040.09 of pending allowance funds, raising the contract from $238,475.00 to $250,271.39. It also extends the end date to August 21, 2026.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Next Generation of Builders, LLC · Santa Clara, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 1, 2026 – Aug 21, 2026
- This vote
- $11,796.39
- Previous total
- $238,475
- New total
- $250,271.39
- Schools
- Markham Elementary School
- Funding
- Fund 140, Deferred Maintenance
- Resource / site
9914/9080-138- Vendor no.
009085- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1716· agendaR.-5- Outcome
- Adopted on the General Consent Report, Sep 9, 2026
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Next Generation of Builders, LLC, Santa Clara, CA, resulting “in a net addition of $11,796.39 to the contract amount after applying $1,040.09 in available pending allowance funds towards PCO#4, based on the following adjustments totaling $12,836.48: 1. PC0#4 Concrete Demolition and Replacement (+$7,308.88): Unforeseen conditions requiring demolition of existing concrete slab in front of the urinals. placement of new reinforced concrete, and restoration of the-affected area for subsequent flooring installation. 2. PCO#5 Toilet Flange Repair (+$1,321.66): Added for replacement of a damaged and deteriorated existing toilet flange discovered during restroom demolition. Work includes removal of unsuitable flange components and installation of a new commercial-grade flange, to allow proper installation of the new toilet fixture. 3. PC0#6 ASI 03 - Ceiling Conduit Support (+$2,380.82): Added for installation of additional conduit supports per ASI 03, including 3/4" J-hangers, threaded rods. anchors, and related electrical support work required for new conduits above the restroom ceiling based on the City Electric Service layout. 4. PC0#7 Bathroom Lighting Fixture Upgrade (+$1,825.12): Added for the cost difference between the originally proposed Lithonia F1/F1A bathroom light fixtures and the architect-requested Prudential BOLT PRO LED fixtures.” for the latter to provide foretasted additional work, as part of the Markham Elementary School Boys Toilet Renovation Project, in the not-to-exceed net amount of $11,796.39, increasing the contract price from $238,475.00 to $250,271.39 and extending the Agreement term from June 1, 2026, through July 31, 2026, to August 21, 2026, an extension of twenty-three (23) calendar days. All other terms and conditions of the Agreement remain unchanged and in full force and effect.
History
- Adopted on the General Consent Report