Cuts $2.02M from Syserco's CAL Shape design-build contract, lowering it to $7.8M
Change Order No. 6 reduces the Syserco Energy Solutions, Inc. design-build contract for the CAL Shape project by a net $2,021,327.02, from $9,837,080.68 to $7,815,753.66. The main change is a $2,033,894.75 deduction across 78 OUSD sites to reflect work actually completed compared with initial estimates. Small additions cover extra repairs at one school and extra cost for installing CO2 sensors during second shift in active classrooms.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Adopted in its own vote at this meeting (6–0, 1 abstaining), instead of with the rest of the consent report.
· Adopted (passed). A motion was made by Director Latta, seconded by Director Berry, that this Change Order No. 6, Agreement Between Owner and Contractor by and between the District and Syserco Energy Solutions, Inc., be Adopted. The motion carried by the following vote:.
- Andrew Bloch Absent
- Amina Tongun Absent
- Rachel Latta Aye
- VanCedric Williams Aye
- Mike Hutchinson Abstained
- Patrice Berry Aye
- Clifford Thompson Aye
- Valarie Bachelor Aye
- Jennifer Brouhard Aye
- Vendor / partner
- Syserco Energy Solutions, Inc. · Fremont, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $2,021,327.02
- Previous total
- $9,837,080.68
- New total
- $7,815,753.66
- Funding
- Reduction In Fiscal Impact - Fund 21 Building Funds, Measure Y
- Resource / site
9657/9000- Vendor no.
004166- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-1734· agendaR.-6- Outcome
- Adopted, Sep 9, 2026
Official text
Approval by the Board of Education of Change Order No. 6, Agreement Between Owner and Contractor by and between the District and Syserco Energy Solutions, Inc., Fremont, CA, providing “… a net deduction of $2,021,327.02 from the contract amount, based on the following adjustments: 1. Ventilation Scope Reduction (-$2,033,894.75): Deducted across 78 OUSD sites to reflect actual completed work versus initial estimates. 2. Additional Contingency Repairs (+$644.87): Added for the installation of additional contingency repairs (filters/A&M) at Manzanita Seed. 3. Second Shift Work Adjustment (+$11,922.86): Added to cover the premium/cost differential for installing CO2 sensors during second shift in active classrooms. reducing the Agreement from $9,837,080.68 to $7,815,753.66, for the CAL Shape Design-Build Facilities Planning and Management Project. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted