Adds $19,743.61 to Next Generation of Builders' Markham Elementary boys' restroom renovation and extends it 40 days
This change order pays Next Generation of Builders for extra work on the Markham Elementary boys' restroom renovation: removing hallway tile, work on a drinking fountain, and trim, cleaning, ceiling and paint work around windows. It raises the contract from $250,271.39 to $270,015.00 and extends the end date by 40 days, from August 21 to September 30, 2026. The work is paid from deferred maintenance funds, and the new end date falls before this October 28, 2026 board meeting.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Taken off the consent vote, then approved on a later consent report on November 12.
· Withdrawn. Withdrawn.
· Adopted on the General Consent Report (passed). A motion was made by Director Latta, seconded by Director Thompson, to Approve the General Consent Report.
- Vendor / partner
- Next Generation of Builders, LLC · Santa Clara, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jul 29, 2026 – Sep 30, 2026
- This vote
- $19,743.61
- Previous total
- $250,271.39
- New total
- $270,015
- Schools
- Markham Elementary School
- Funding
- Fund 140, Deferred Maintenance
- Resource / site
9914/9080- Vendor no.
009085- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-2124· agendaR.-7- Outcome
- Adopted on the General Consent Report, Nov 12, 2026
Official text
Approval by the Board of Education of Change Order No. 2, Agreement Between Owner and Contractor by and between the District and Next Generation of Builders, LLC, Santa Clara, CA, for the latter to provide additional work for PCO#lO Hallway Tile Abatement and Drinking fountain and PCO# 11 Trim/Cleaning Around Windows, Ceiling, and paint for the Markham Elementary School Boys Toilet Renovation Project, in the not-to-exceed amount of $19,743.61, increasing the contract price from $250,271.39 to $270,015.00. The Change Order also extends the contract term from July 29, 2026, through August 21, 2026, to September 30, 2026, an extension of forty (40) calendar days. All other terms and conditions of the Agreement remain unchanged and in full force and effect.
History
- Withdrawn
- Adopted on the General Consent Report
Also on the agenda: Nov 12, 2026