Adds $647,761 to Cahill Contractors' Fremont High modernization contract and extends it to Aug. 31, 2026
This change order pays Cahill Contractors for extra construction work in Phase II of the Fremont High School modernization, under a lease-leaseback construction contract. The work covers a wall height conflict at the driveway, an unknown gas pipe, fire alarm changes, dry-rot repairs at the auditorium entrance, and added site management costs from auditorium and project delays. The contract rises from $11,757,368.71 to $12,405,129.76, and the end date moves from June 30, 2026 to Aug. 31, 2026, which is before this vote.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Cahill Contractors, LLC · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 26, 2024 – Aug 31, 2026
- This vote
- $647,761.05
- Previous total
- $11,757,368.71
- New total
- $12,405,129.76
- Schools
- Fremont High School
- Funding
- Fund 21 Building Fund, Measure J
- Resource / site
9650/9921- Vendor no.
009054- Presented by
- Deputy Chief, Facilities Planning and Management
- File
26-2190· agendaR.-10- Outcome
- Adopted on the General Consent Report, Oct 28, 2026
Official text
Approval by the Board of Education of Change Order No. 3, Lease-Leaseback Contract by and between the District and Cahill Contractors, LLC, Oakland, CA, for the latter to provide additional construction services for the Phase II scope, PCOs 13-17 including the following changes: RFI 59-59.2 Conflicts with Bioretention Wall Elevations at Driveway; RFI 57 Unknown Gas Pipe Near Pile #43; CCD-011A Fire Alarm Changes, Modular Pathway to FACP; Dry-Rot Repairs at Auditorium Bldg. Entrance; and Extended GCs for Auditorium & Project Delays, as identified in PCO’s No.13 thru 17, increasing the Lease-Leaseback Contract amount by $647,761.05, from $11,757,368.71 to $12,405,129.76 and extending the term of the Contract from September 26, 2024 through June 30, 2026 to August 31, 2026, extending term by 62 calendar days, for the Fremont High School Modernization Project. All other terms and conditions of the Agreement remain in full force and effect.