Adds $291,282 and extends Viatron's scanning of district records through December 2023
Viatron Systems, Inc. of Gardena scans and archives a large quantity of confidential district records for the Central Office 1000 Broadway Digitalization Project. This amendment adds $291,282, which includes up to $37,993 for additional services, and raises the limit from $640,660 to $931,942. It also extends the end date from August 31, 2023 to December 31, 2023.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Adopted in its own vote at this meeting (5–1), instead of with the rest of the consent report.
· Adopted (passed). A motion was made by Director Davis, seconded by Vice President Thompson, that this Agreement or Contract be Adopted. The motion carried by the following vote:.
- Linh Le Absent
- Natalie Gallegos Chavez Absent
- Benjamin "Sam" Davis Aye
- Jennifer Brouhard Aye
- VanCedric Williams Nay
- (Vacancy) (Vacancy) Non-voting
- Valarie Bachelor Aye
- Clifford Thompson Aye
- Mike Hutchinson Aye
- Vendor / partner
- Viatron Systems, Inc. · Gardena, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- Food, transportation & operations
- Term
- Jun 30, 2022 – Dec 31, 2023
- This vote
- $291,282
- Previous total
- $640,660
- New total
- $931,942
- Funding
- Fund 01 General Fund
- Resource / site
0901 918- Vendor no.
007248- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-1275· agendaT.-8- Outcome
- Adopted, Jun 21, 2023
Official text
Approval by the Board of Education of Amendment No.2, General Services Agreement by and between the District and Viatron Systems, Inc., Gardena, CA, for the latter to provide continued scanning and archiving services needed for a large quantity of confidential records for the District, as described in the Proposal attached to this Amendment as Exhibit A, for the Central Office 1000 Broadway Digitalization Project, in an additional amount of $291,282.00, which includes a not to exceed contingency fee of $37,993.00 for Additional Services, increasing the not-to-exceed amount of the Agreement from $640,660.00 to $931,942.00, and extending the term of the Agreement from June 30, 2022 through August 31, 2023 to December 31, 2023 (an additional 122 calendar days). All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted