Adds $726,766 to Arntz Builders' contract for the Cole Campus Central Administration Center
This change order pays Arntz Builders for additional construction work covered by several preliminary change orders (PCOs) on the Cole Campus Central Administration Center Project. It raises the contract price from $38,572,174.81 to $39,298,940.56. All other terms stay the same.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Arntz Builders, Inc. · Petaluma, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $726,765.75
- Previous total
- $38,572,174.81
- New total
- $39,298,940.56
- Funding
- Fund 21 Building Fund, Measure Y
- Resource / site
9655-109- Vendor no.
000493- Presented by
- Facilities Committee
- File
23-1146· agendaU.-2- Outcome
- Adopted on the General Consent Report, Aug 23, 2023
Official text
Approval by the Board of Education of Change Order No. 2, Agreement Between Owner and Contractor by and between the District and Arntz Builders, Inc., Petaluma, CA, for additional construction services which includes PCO's 2-14, 16-25, 27, and 29 for various contract changes, for the Cole Campus Central Administration Center Project, in the amount of $726,765.75, increasing the contract price from $38,572,174.81 to $39,298,940.56. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report