Arntz Builders, Inc.

OUSD vendor no. 000493OrganizationPetaluma, CAOn the consent report Jun 22, 2022 – May 14, 2025

$38.8Mnot to exceed, approved on consent
12items approved on consent
15official Legistar records, all years

About this vendor

A general contractor based in Petaluma, California, that builds commercial and public works projects in Northern California. It does both new construction and renovation work.

Registered name
Arntz Builders, Inc.
Type
Company
Address
431 Payran Street, Petaluma, CA 94952

Researched by AI from public sources on Oct 2, 2026, checked by a second, independent AI review, with every contact detail matched to a cited page. Not from OUSD or Legistar; may be incomplete or out of date. Sources: Arntz Builders, Inc., Arntz Builders, Inc. Contact, Central Administrative Center at Cole Campus.

What the district contracts them for

  • School buildings & construction 12
  • Change order 9
  • Bid award 3

Categories and action types are this tool's classification (AI-assigned, then checked), not Legistar fields. How this works.

Official information from Legistar

Legistar has no vendor profile; a vendor appears only as the vendor number on each record. These fields come from the official records listed at the bottom of this page.

OUSD vendor number
000493
Named in the agenda text as
Arntz Builders, Inc.
Presenting offices
Deputy Chief, Facilities Planning and Management (13); Community Advisory Committee-Programs for Exceptional Children (1); Facilities Committee (1)
Record types
Agreement or Contract (14); Discussion Item (1)
Funding sources
9655/9805; Fud 21 Building Fund Measure Y; Fund 21 Building Fund Measure Y; Fund 21 Building Fund, Measure Y; Fund 21 Building Funds Measure Y; Fund 21 Building Funds, Measure Y; Fund 21, Building Fund Measure Y; Fund 21, Measure J; Fund 21/Measure Y
Resource / site codes
9650-1099655 1099655 1319655 1999655 2019655 2129655-1099655/1099655/1319655/9805

Approved on the consent report (12)

  1. Adds $440,000 and 296 days to Arntz Builders' Claremont Middle School kitchen and multi-purpose room jobMay 14, 2025 · M.-3 · 25-0927 · Jun 23, 2022 – Aug 9, 2024 · Adopted on the General Consent ReportAfter work beganRaises existing contractMulti-year
    +$440Knew total $16.7M
  2. Adds $202,130.36 to Arntz Builders' contract for extra work on Claremont Middle School's kitchen projectMar 26, 2025 · M.-1 · 25-0462 · Adopted on the General Consent ReportRaises existing contract
    +$202Knew total $16.3M
  3. Adds $500,000 and 330 days to Arntz Builders' Laurel Child Development Center jobJan 8, 2025 · M.-5 · 24-2951 · Jun 23, 2022 – Aug 16, 2024 · Adopted on the General Consent ReportAfter work beganRaises existing contractMulti-year
    +$500Knew total $14.7M
  4. Adds $72,307.84 to Arntz Builders' Claremont Middle School kitchen projectJan 8, 2025 · M.-8 · 24-2981 · Adopted on the General Consent ReportRaises existing contract
    +$72Knew total $16.1M
  5. Adds $355,279 for Arntz Builders' extra work on the Cole Campus administration centerJun 26, 2024 · U.-6 · 24-1464 · Adopted on the General Consent ReportRaises existing contract
    +$355Knew total $43.6M
  6. Adds $889,233.18 to Arntz Builders' contract for the new Cole Campus district office buildingMay 22, 2024 · U.-7 · 24-1086 · Adopted on the General Consent ReportRaises existing contract
    +$889Knew total $43.2M
  7. Adds $726,923.26 to Arntz Builders' contract for the new Cole Campus administration buildingNov 16, 2023 · E.-14 · 23-2441 · Adopted on the General Consent ReportAfter work beganRaises existing contract
    +$727Knew total $40M
  8. Adds $726,766 to Arntz Builders' contract for the Cole Campus Central Administration CenterAug 23, 2023 · U.-2 · 23-1146 · Adopted on the General Consent ReportRaises existing contract
    +$727Knew total $39.3M
  9. Awards Arntz Builders $1.93M for site work for Roosevelt Middle School's portables and science buildingMay 24, 2023 · U.-6 · 23-1144 · May 25, 2023 – Jul 31, 2023 · Adopted on the General Consent Report
    $1.93M
  10. Adds $2.82M to Arntz Builders' Cole Campus contract for contaminated soil removalNov 30, 2022 · T.-1 · 22-2475 · AdoptedVoted on separatelyRaises existing contract
    +$2.82Mnew total $38.6M
  11. Awards Arntz Builders $15.99M to build Claremont Middle School's multi-purpose room and kitchenJun 22, 2022 · V1.-1 · 22-1167 · Jun 23, 2022 – Aug 31, 2023 · Adopted on the General Consent ReportMulti-year
    $16M
  12. Awards Arntz Builders $14.17M to replace the Laurel Child Development CenterJun 22, 2022 · V1.-3 · 22-1325 · Jun 23, 2022 – Sep 21, 2023 · Adopted on the General Consent ReportMulti-year
    $14.2M

All Legistar records (15)

Every Legistar record carrying this vendor number in any year, on consent or not, plus records Legistar links to this vendor's consent items (for example, an amendment's original agreement). Newest first.

DateFileOfficial titleTypeStatus
Dec 31, 202524-0186Community Advisory Committee - Special Education AnnouncementsCommunity Advisory Committee-Programs for Exceptional Children · Related: 24-1464Discussion ItemCommittee, New Business
May 14, 202525-0927Change Order No. 3, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Claremont Middle School Multi-Purpose Room & Kitchen Project –Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 25-0718 · Related: 22-1167, 24-2981, 25-0462 · Plain-English summaryAgreement or ContractPassed
Mar 26, 202525-0462Change Order No. 2, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Claremont Middle School Multi-Purpose Room & Kitchen Project –Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 25-0421 · Related: 25-0927 · Plain-English summaryAgreement or ContractPassed
Jan 8, 202524-2981Change Order No. 1, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Claremont Middle School Multi-Purpose Room & Kitchen Project – Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 24-2383 · Related: 22-1167, 25-0927 · Plain-English summaryAgreement or ContractPassed
Jan 8, 202524-2951Changer Order No. 1, Agreement Between Owner and Contractor - Arntz Builders, Inc. – Laurel Child Development Center (CDC) Replacement Project – Division of Facilities Planning & ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 24-2380 · Plain-English summaryAgreement or ContractPassed
Jun 26, 202424-1464Change Order No. 6, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Cole Campus Central Administration Center Project–Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 24-1345 · Related: 21-1746, 22-2475, 23-1146, 23-2441, 23-2701, 24-0186 · Plain-English summaryAgreement or ContractPassed
May 22, 202424-1086Change Order No. 5, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Cole Campus Central Administration Center Project–Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 24-1052 · Plain-English summaryAgreement or ContractPassed
Jan 24, 202423-2701Change Order No. 4, Agreement Between Owner and Contractor - Arntz Builders, Inc. - Cole Campus Central Administration Center Project - Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 24-0101 · Related: 22-2475, 23-1146, 23-2441, 24-1464Agreement or ContractPassed
Nov 16, 202323-2441Change Order No. 3, Agreement Between Owner and Contractor - Arntz Builders, Inc. - Cole Campus Central Administration Center Project - Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 23-1943 · Related: 23-2701, 24-1464 · Plain-English summaryAgreement or ContractPassed
Aug 23, 202323-1146Change Order No. 2, Agreement Between Owner and Contractor – Arntz Builders, Inc. – Cole Campus Central Administration Center Project–Division of Facilities Planning and ManagementFacilities Committee · Enactment no. 23-1486 · Related: 23-2701, 24-1464 · Plain-English summaryAgreement or ContractPassed
May 24, 202323-1144Agreement Between Owner and Contractor – Arntz Builders, Inc. – Roosevelt Middle School Modernization- Interim Housing Increment 1 and Science Modular Building Increment 1 Project – Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 23-1055 · Plain-English summaryAgreement or ContractPassed
Nov 30, 202222-2475Change Order No. 1, Agreement Between Owner and Contractor - Arntz Builders, Inc.. - Cole Campus Central Administration Center Project - Division of Facilities Planning and ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 22-2065 · Related: 23-2701, 24-1464 · Plain-English summaryAgreement or ContractPassed
Jun 22, 202222-1325Agreement Between Owner and Contractor - Competitively Bid – Arntz Builders, Inc. – Laurel Child Development Center (CDC) Replacement Project – Division of Facilities Planning & ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 22-1341 · Plain-English summaryAgreement or ContractPassed
Jun 22, 202222-1167Agreement Between Owner and Contractor - Competitively Bid - Arntz Builders, Inc. - Claremont Middle School Multi-Purpose Room & Kitchen Project - Division of Facilities Planning & ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 22-1339 · Related: 24-2981, 25-0927 · Plain-English summaryAgreement or ContractPassed
Jun 30, 202121-1746Agreement Between Owner and Contractor - Competitively Bid –Arntz Builders, Inc. – Cole Campus Central Administration Center Project – Division of Facilities Planning & ManagementDeputy Chief, Facilities Planning and Management · Enactment no. 21-1188 · Related: 24-1464Agreement or ContractPassed

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.