Change order adds $4,250 to DecoTech's door entry project at 900 High Street
This change order has DecoTech Systems provide, install and test a fiber cable linking the main and custodial network rooms for the 900 High Street Door Entry Systems Project. It adds $4,250 and changes the adjusted contract price from $49,882.90 to $54,132.90. All other terms stay the same.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- DecoTech Systems · Walnut Creek, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $4,250
- Previous total
- $49,882.90
- New total
- $54,132.90
- Funding
- Fund 21, Building Funds Measure B
- Resource / site
9799 918- Vendor no.
001325- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-1791· agendaU.-10- Outcome
- Adopted on the General Consent Report, Sep 13, 2023
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and DecoTech Systems., Walnut Creek, CA, for the latter to provide, install, test and terminate one 6-strand OS2 Armored Fiber backbone from the MDF to the new custodial IDF, for the 900 High Street Door Entry Systems Project, in the amount of $4,250.00, changing the adjusted contract price, less any allowances or contingency, from $49,882.90 to $54,132.90. All other terms and conditions of the Agreement remain in full force and effect.