Raises existing contract
+$889Knew total $43.2M

Adds $889,233.18 to Arntz Builders' contract for the new Cole Campus district office building

This change order pays Arntz Builders, Inc. for extra construction work on the new two-story building for district staff at the Cole Campus Central Administration Center. The work covers preliminary change orders (PCOs) 57 through 77. It raises the contract price from $42,341,329.88 to $43,230,563.06.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Change order
Category
School buildings & construction
This vote
$889,233.18
Previous total
$42,341,329.88
New total
$43,230,563.06
Funding
Fund 21 Building Fund Measure Y
Resource / site
9655 199
Vendor no.
000493
Presented by
Deputy Chief, Facilities Planning and Management
File
24-1086 · agenda U.-7
Outcome
Adopted on the General Consent Report, May 22, 2024

Official text

Approval by the Board of Education of Change Order No. 5, Agreement Between Owner and Contractor by and between the District and Arntz Builders, Inc., Petaluma, CA, for the latter to provide additional construction services which includes PCO's 57 through 77, constructing a new two-story building for District Staff, for the Cole Campus Central Administration Center Project, in the amount of $889,233.18, increasing the contract price from $42,341,329.88 to $43,230,563.06.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.