Adds $355,279 for Arntz Builders' extra work on the Cole Campus administration center
Change Order No. 6 covers extra construction work on the new two-story district staff building at the Cole Campus Central Administration Center. It bundles several preliminary change orders (PCOs 78 through 99 and 101 through 109) and raises the contract price from $43,230,563.06 to $43,585,841.57.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Arntz Builders, Inc. · Petaluma, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $355,278.51
- Previous total
- $43,230,563.06
- New total
- $43,585,841.57
- Schools
- Cole Campus Central Administration Center
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9655 109- Vendor no.
000493- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-1464· agendaU.-6- Outcome
- Adopted on the General Consent Report, Jun 26, 2024
Official text
Approval by the Board of Education of Change Order No. 6, Agreement Between Owner and Contractor by and between the District and Arntz Builders, Inc., Petaluma, CA, for additional construction services which includes PCO's 78 through 99 and 101 through 109, as described therein, for construction of a new two-story building for District Staff, for the Cole Campus Central Administration Center Project, in the amount of $355,278.51, increasing the contract price from $43,230,563.06 to $43,585,841.57. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report