Adds $500,000 and 330 days to Arntz Builders' Laurel Child Development Center job
The Board approves a change order for Arntz Builders on the Laurel Child Development Center replacement. It adds up to $500,000.00 for extended general conditions (office and field overhead, materials and equipment), raising the not-to-exceed amount from $14,174,463.00 to $14,674,463.00. It also extends the term by 330 calendar days, through August 16, 2024.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Arntz Builders, Inc. · Petaluma, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 23, 2022 – Aug 16, 2024
- This vote
- $500,000
- Previous total
- $14,174,463
- New total
- $14,674,463
- Schools
- Laurel Child Development Center
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9655/131- Vendor no.
000493- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-2951· agendaM.-5- Outcome
- Adopted on the General Consent Report, Jan 8, 2025
Official text
Approval by the Board of Education of Change Oder No. 1, Agreement Between Owner and Contractor by and between the District and Arntz Builders, Inc., Petaluma, CA, for the latter to perform Extended General Conditions COR#73, as described therein, incorporated herein by reference as though fully set forth (i.e., provide office and field overhead expenses, materials and equipment, etc.), for the Laurel Child Development Center (CDC) Replacement Project, in the not to exceed additional amount of $500,000.00, increasing the Agreement not to exceed amount from $14,174,463.00 to $14,674,463.00, and extending the term of the Agreement, for an additional 330 calendar days, from June 23, 2022, to September 21, 2023, through August 16, 2024. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report