Adds $16,268 to Deco Tech Systems' 900 High Street phone and data cabling job
This change order adds extra cabling for three data connections at two voice/data locations and wireless access points in the Skilled Labor Office and metal shop, plus a backup power supply, at 900 High Street. The district requested the added work through a preliminary change order. The contract price rises from $96,060.37 to $112,328.37.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Deco Tech Systems · Walnut Creek, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $16,268
- Previous total
- $96,060.37
- New total
- $112,328.37
- Funding
- Fund 21 Building Fund Measure J
- Resource / site
9650 918- Vendor no.
001325- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-3149· agendaM.-8- Outcome
- Adopted on the General Consent Report, Jan 22, 2025
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor, by and between the District and Deco Tech Systems, Walnut Creek, CA, for owner requested additional cabling installation for three data drops (at two voice/data locations and at WAP locations at the skilled Labor Office Room 1100 and the metal shop, and installation of Uninterrupted Power Supply (UPS) at 900 High Street. PCO 1, for the 900 High Street VOIP Cabling Project, in the not-to-exceed amount of $16,268.00, increasing the Agreementt price from $96,060.37 to $112,328.37. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report