Extends Data Media Services' Westlake Middle School security contract to November 30, 2025
The board approves a change order that gives Data Media Services more time to finish the Westlake Middle School Security Improvement Project. The end date moves from January 2025 to November 30, 2025, which is 305 more days. The contract amount does not change.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Notes on the official text
- The text prints the prior end date as "January 29, 29025", an evident typo for January 29, 2025, which is consistent with the stated 305-day extension to November 30, 2025.
- Vendor / partner
- Data Media Services, Inc. · Stockton, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Oct 31, 2024 – Nov 30, 2025
- Schools
- Westlake Middle School
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9657 213- Vendor no.
006952- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-2469· agendaP.-6- Outcome
- Adopted on the General Consent Report, Nov 12, 2025
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Data Media Services, Inc., Stockton, CA, providing for an extension to the term of the Agreement from October 31, 2024, through January 29, 29025, to November 30, 2025 (an additional 305 calendar days), as identified in the PCO No. 1, for the Westlake Middle School Security Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report